Fog Seal Application Checklist
(Courtesy of the Foundation for Pavement Preservation
& FHWA)
Printed copies are available from FHWA and FP2 at
www.pavementpreservation.org
Click here for a downloadable copy of the Fog Seal Checklist
Click here for a downloadable copy of the Rejuvenator Checklist
Preliminary Responsibilities
Project Review
¨ Is the project a good candidate for a fog seal?
¨ What is the existing surface type?
¨ Has an assessment been made of the
surface absorption?
¨ Has much stone been lost?
¨ How much bleeding or flushing exists?
¨ Review project for bid/plan quantities.
¨ What is the relative cost?
Document Review
¨ Bid specifications
¨ Special provisions
¨ Agency requirements
¨ Emulsion specifications
¨ Traffic control plan
¨ Material safety data sheets
o Exercise care if coal tar oils are
included in formulation
Materials Checks
Asphalt emulsion selection: type and dilution rate.
¨ The emulsion is from an approved source
(if required).
¨ The emulsion is sampled and submitted for
testing (if required).
¨ The dilution water to be used is compatible
with the emulsion.
¨ The emulsion temperature is within
application temperature specifications.
¨ Sand, if required, is within specifications
and dry.
Pre-application Inspection Responsibilities
Surface Preparation
¨ The surface is clean and dry.
¨ All pavement distresses have been repaired.
¨ The existing surface has been inspected
for drainage problems.
Equipment Inspections
Broom for Cleaning Existing Surface
¨ Bristles are the proper length.
¨ The broom can be adjusted vertically to
avoid excess pressure.
Spray Distributor
¨ The spray bar is at the proper height.
¨ All nozzles are uniformly angled 15° to 30°
from the spray bar.
¨ All nozzles are free of clogs.
¨ The spray pattern for uniformity and
proper overlap (double or triple) has
been checked.
¨ Application pressure has been checked.
¨ The distributor’s application calibration
has been checked.
¨ There is a working and calibrated
thermometer on site.
¨ Water has been added to the emulsion in
correct proportion and circulated.
There is no foam.
Sand Spreader
¨ Each gate control and settings have been
checked.
¨ Sand is free flowing.
¨ The chip spreader’s calibration across the
entire chipper head has been checked.
¨ The truck hookup hitches have been checked.
Haul Trucks
¨ The truck box is clean and free of debris and
other materials.
¨ The truck hookup hitch is in working order.
¨ If a truck box apron or extension is required
for loading the sand spreader, it is available.
All Equipment
¨ All equipment is free of leaks.
¨ All equipment is calibrated and clean.
Weather Requirements
¨ The minimum surface and air temperature
requirements have been met (default 15°C; 59°F).
¨ Air and surface temperatures have been checked
at the coolest location on the project.
¨ Air and surface temperatures meet agency
requirements.
Note: High winds can create problems with the diluted
emulsion application.
Note: High temperatures, humidity, and wind will affect
how long the emulsion takes to break.
¨ The application of emulsion does not begin if
rain is likely.
Determining Application Rates
¨ Agency guidelines and requirements are being
followed.
¨ The absorption ability of the surface has been
checked.
¨ More emulsion can be applied to dried-out and
porous surfaces.
¨ More emulsion can be applied on roads with low
traffic volumes.
¨ Do not apply to smooth, nonporous, and
asphalt-rich surfaces.
¨ Less emulsion must be applied on roads with
high traffic volumes.
¨ Does the emulsion soak into the surface?
¨ If the texture is high, spray should be in both
directions to avoid rain-shadow effects.
Method for Determining Emulsion Application Rates
¨ To get an idea of where the application rate range
should be:
¨ Take a 1/2 L can of diluted emulsion and
pour it evenly over an area about 1 m2
(or take a 1 pint can of the diluted emulsion
and pour it evenly over an area about 1 yd2).
(Note: conversions are approximate.)
¨ If the emulsion is not absorbed into the
surface, decrease the amount and apply to
a new 1 m2 (or 1 yd2) area. Repeat the
trials until the approximate application rate
is found.
¨ If the surface looks like it will absorb more
emulsion, increase the amount and apply
over a new 1 m2 (or 1 yd2) area.
¨ Repeat trials until the approximate application
rate is found.
Checking Application Rates
Emulsion Method A (RECOMMENDED FOR CALIBRATION)
¨ Record the weight of a .84 m2 (1 yd2) pan or nonwoven
geotextile material.
¨ Place the pan or geotextile on the road surface.
¨ Have the distributor apply emulsion over the pan or
geotextile.
¨ Record the weight of the pan and emulsion or the
geotextile
with emulsion.
¨ Subtract the two weights to determine the weight
of the emulsion applied.
Emulsion Method B
(RECOMMENDED FOR RANDOM CHECKS)
¨ Park the distributor on level ground. Measure
and record the number of L (gal) of emulsion.
¨ Measure off a known area for a test section.
¨ Have the distributor apply emulsion to
the test section.
¨ Park the distributor on level ground and
remeasure the emulsion.
¨ Subtract the two measurements to obtain the
volume of emulsion applied.
¨ To determine the application rate, divide the
amount of emulsion applied by the test area—L/m2
or gal/yd2 (if using feet, length x width/9 = yd2).
Traffic Control
¨ The signs and devices used match the traffic control plan.
¨ The setup complies with local agency requirements
or the Federal Manual on Uniform Traffic Control
Devices (MUTCD).
¨ Flaggers do not hold the traffic for extended
periods of time.
¨ Any unsafe conditions are reported to a supervisor
(contractor or agency).
¨ The pilot car leads traffic slowly—40 kph (24 mph)
or less—over the fresh seal coat.
¨ Signs are removed or covered when they no longer apply.
Project Inspection Responsibilities
Sand Application (where used)
¨ Enough trucks are on hand to keep a steady
supply of sand f
or the spreader.
¨ Application starts and stops with neat,
straight edges.
¨ Application starts and stops on building paper.
¨ No emulsion is on top of the sand.
¨ Application is stopped as soon as any problems
are detected.
¨ Application appears uniform.
¨ Checks are made for streaks and plug-ups.
Emulsion Application
¨ Building paper is used to start and stop
emulsion application for straight edges.
¨ Emulsion is within the required application
temperature range.
¨ Application appears uniform.
¨ Checks are made for drilling and streaking.
¨ Nozzles are checked for plugging.
¨ Random application rate checks are performed.
¨ The distributor adjusts speed to match chip
spreader speed to prevent stop-start operations.
¨ The distributor is stopped if any problems are
observed.
Truck Operation
¨ Trucks are staggered across the fresh fog seal
coat to avoid driving over the same area.
¨ Trucks travel slowly on the fresh seal.
¨ Stops and turns are made gradually.
¨ Truck operators avoid driving over exposed
emulsion.
Brooming
¨ Brooming begins as soon as possible only if
sand is applied.
¨ Brooming should be light and done once to
remove excess only.
Opening the Fog Seal to Traffic
¨ Traffic travels slowly—40 kph (24 mph) or less—
over the fresh seal until seal is broomed and opened
for normal traffic.
¨ Reduced speed limit signs are used when pilot cars
are not used.
¨ After brooming, pavement markings are applied
before opening
pavement to normal traffic.
¨ All construction-related signs are removed when
opening pavement to normal traffic.
Cleanup Responsibilities
¨ All loose sand from brooming is removed from
the travel way.
¨ Excessive emulsion application or spills are removed.
Common Problems and Solutions
Excessive splattering of the emulsion:
1. Emulsion has been diluted too much.
2. Bar is incorrectly set.
3. Spray pressure is too high.
Streaking or drill marks are appearing in emulsion:
1. Emulsion is too cold.
2. Viscosity of the emulsion is too high.
3. All nozzles are not at the same angle.
4. Spray bar is too high.
5. bar pressure is too high.
6. Nozzle is plugged.
Emulsion bleeding or flushing occurs:
1. Emulsion application is too high.
Sources: Information in this checklist is based on or
refers to the following sources:
Application Guides. 1992.
Asphalt Emulsion Manufacturers Association.
Annapolis, MD
Asphalt Emulsion Handbook, Manual Series No. 4. 2000.
Lexington, KY: The Asphalt Institute.
Basic Asphalt Emulsion Manual,
Manual Series No. 19. 1999.
Lexington, KY: The Asphalt Institute.
Manual on Uniform Traffic Control Devices,
Millennium Edition. 2000.
Washington, DC:
Federal Highway Administration.
Rejuvenator Seal Application Checklist
Preliminary Responsibilities
Project Review
¨ Is the project a good candidate for a rejuvenator
seal?
¨ Has the friction been tested; is the expected
reduction in friction acceptable?
¨ What is the existing surface type?
¨ Has an assessment been made of the surface
absorption?
¨ Has much stone been lost?
¨ Does bleeding or flushing exist?
¨ Review project for bid/plan quantities.
¨ What is the relative cost?
Document Review
¨ Bid specifications
¨ Special provisions
¨ Agency requirements
¨ Emulsion specifications
¨ Traffic control plan
¨ Material safety data sheets
o Exercise care if coal tar oils are included in
formulation
Materials Checks
Asphalt emulsion selection: type and dilution rate.
¨ The emulsion is from an approved source (if required).
¨ The emulsion is sampled and submitted for testing
(if required).
¨ The water to be used is compatible with the emulsion.
¨ The emulsion temperature is within application
temperature specifications.
¨ Sand, if required, is within specifications and dry.
Pre-application Inspection Responsibilities
Surface Preparation
¨ The surface is clean and dry.
¨ All pavement distresses have been repaired.
¨ The existing surface has been inspected for drainage
problems.
Equipment Inspections
Broom for Cleaning Existing Surface
¨ Bristles are the proper length.
¨ The broom can be adjusted vertically to avoid excess
pressure.
Spray Distributor
¨ The spray bar is at the proper height.
¨ All nozzles are uniformly angled 15° to 30° from the
spray bar.
¨ All nozzles are free of clogs.
¨ The spray pattern for uniformity and proper overlap
(double or triple) has been checked.
¨ Application pressure has been checked.
¨ The distributor’s application calibration has been
checked.
¨ There is a working and calibrated thermometer
on site.
¨ Water has been added to the emulsion in correct
proportion and circulated. There is no foam.
Sand Spreader
¨ Each gate control and settings have been checked.
¨ Sand is free flowing.
¨ The chip spreader’s calibration across the entire
chipper head has been checked.
¨ The truck hookup hitches have been checked.
Haul Trucks
¨ The truck box is clean and free of debris and other
materials.
¨ The truck hookup hitch is in working order.
¨ If a truck box apron or extension is required for
loading the sand spreader, it is available.
All Equipment
¨ All equipment is free of leaks.
¨ All equipment is calibrated and clean.
Weather Requirements
¨ The minimum surface and air temperature
requirements have been met (default 15 °C; 59 °F).
¨ Air and surface temperatures have been checked
at the coolest location on the project.
¨ Air and surface temperatures meet agency
requirements.
Note: High winds can create problems with the diluted
emulsion application.
Note: High temperatures, humidity, and wind will affect
how long the emulsion takes to break.
¨ The application of emulsion does not begin if rain
is likely.
Determining Application Rates
¨ Agency guidelines and requirements are being
followed.
¨ The absorption ability of the surface has been
checked.
¨ More emulsion can be applied to dried-out and
porous surfaces.
¨ More emulsion can be applied on roads with low
traffic volumes.
¨ Do not apply to smooth, nonporous, low friction
and asphalt-rich surfaces.
¨ Less emulsion must be applied on roads with
high traffic volumes.
¨ Does the emulsion soak into the surface?
¨ If the texture is high, spray should be in both
directions to avoid rain-shadow effects.
Method for Determining Emulsion Application Rates
¨ To get an idea of where the application rate range
should be:
¨ Take a 1/2 liter can of diluted emulsion
and pour it evenly over an area about 1 m2
(or take a 1 pint can of the diluted emulsion
and pour it evenly over an area about 1 yd2).
(Note: conversions are approximate.)
¨ If the emulsion is not absorbed into the surface,
decrease the amount and apply to a new 1 m2
(or 1 yd2) area. Repeat the trials until the
approximate application rate is found.
¨ If the surface looks like it will absorb more
emulsion, increase the amount and apply
over a new 1 m2 (or 1 yd2) area.
¨ Repeat trials until the approximate application
rate is found.
¨ Alternately, a Ring Test CT 345 (California Method Of
Test For Determining The Quantity Of Asphalt
Rejuvenating Agent Required For An Asphaltic
Pavement.
http://www.dot.ca.gov/hq/esc/ctms/CT_345.pdf)
may be used.
Checking Application Rates
Emulsion Method A (RECOMMENDED FOR CALIBRATION)
¨ Record the weight of a .84 m2 (1 yd2) pan or nonwoven
geotextile material.
¨ Place the pan or geotextile on the road surface.
¨ Have the distributor apply emulsion over the pan or
geotextile.
¨ Record the weight of the pan and emulsion or the
geotextile with emulsion.
¨ Subtract the two weights to determine the weight
of the emulsion applied.
Emulsion Method B
(RECOMMENDED FOR RANDOM CHECKS)
¨ Park the distributor on level ground. Measure and record
the number of L (gal) of emulsion.
¨ Measure off a known area for a test section.
¨ Have the distributor apply emulsion to the test section.
¨ Park the distributor on level ground and remeasure the
emulsion.
¨ Subtract the two measurements to obtain the volume of
emulsion applied.
¨ To determine the application rate, divide the amount of
emulsion applied by the test area—L/m2 or gal/yd2
(if using feet, length x width/9 = yd2).
Traffic Control
¨ The signs and devices used match the traffic control plan.
¨ The setup complies with local agency requirements or
the Federal Manual on Uniform Traffic Control Devices
(MUTCD).
¨ Flaggers do not hold the traffic for extended periods
of time.
¨ Any unsafe conditions are reported to a supervisor
(contractor or agency).
¨ The pilot car leads traffic slowly—40 kph (24 mph) or
less—over the fresh seal coat.
¨ Signs are removed or covered when they no longer
apply.
¨ Traffic is not returned to full speed until the friction
has been tested and judged to be at an acceptable level.
Project Inspection Responsibilities
Sand Application (where used)
¨ Enough trucks are on hand to keep a steady supply
of sand for the spreader.
¨ Application starts and stops with neat, straight edges.
¨ Application starts and stops on building paper.
¨ No emulsion is on top of the sand.
¨ Application is stopped as soon as any problems are
detected.
¨ Application appears uniform.
¨ Checks are made for streaks and plug-ups.
¨ Sand should not be applied until the emulsion has
broken or been completely absorbed into the surface.
Otherwise, the sand may form a low friction slurry
with the emulsion.
Emulsion Application
¨ Building paper is used to start and stop emulsion
application for straight edges.
¨ Emulsion is within the required application
temperature range.
¨ Application appears uniform.
¨ Checks are made for drilling and streaking.
¨ Nozzles are checked for plugging.
¨ Random application rate checks are performed.
¨ The distributor adjusts speed to match chip
spreader speed to prevent stop-start operations.
¨ The distributor is stopped if any problems are
observed.
Truck Operation
¨ Trucks are staggered across the fresh
rejuvenator seal coat to avoid driving
over the same area.
¨ Trucks travel slowly on the fresh seal.
¨ Stops and turns are made gradually.
¨ Truck operators avoid driving over exposed
emulsion.
Brooming
¨ Brooming begins as soon as possible only if
sand is applied.
¨ Brooming should be light and done once to
remove excess only.
Opening the Rejuvenator seal to Traffic
¨ Traffic travels slowly—40 kph (24 mph) or
less—over the fresh seal until seal is broomed
and opened for normal traffic.
¨ |